Skip to Content

SOLAR SYSTEM MEASUREMENT

Check that your system performs as it was designed

Solar system measurement service

No.Service itemTarget / inspectionFrequencyEquipment / measuring instrument / inspection methodUnitApplicable standard
IINSPECTION AND ASSESSMENT OF OPERATING CONDITION OF PV MODULES / STRINGS / DC CABLES
1IV curve test and operating condition assessment of PV strings: / – Open-circuit voltage of PV module (Voc) / – PV module voltage at maximum power point (Vmpp) / – PV module current at maximum power point (Impp) / – Short-circuit current (Isc) / – PV module peak power (Pmax) / – IV curve test of PV module. / – Operating condition assessment of PV module.PV string4 times/yearHT Instruments SOLAR IVe (15A, 1500VDC) / Solmetric PVA-1500stringTCVN / 11855-1:2017 / IEC 62446-1:2017
2Insulation resistance measurement and insulation condition assessment of PV strings: / – Insulation resistance of PV String (+) to Ground. / – Insulation resistance of PV String (-) to Ground. / – Insulation resistance of PV String (+) to PV String (-). / – Condition assessment and potential faults of DC cable system and DC cable trays.PV string4 times/yearHIOKI IR4053stringQCVN QTĐ-5:2009/BCT / IEC 62446-1:2017
3Thermal scanning of PV system to detect anomalies (broken, cracked or shattered PV modules, dirt, scratches, oil stains, objects on modules, physical damage, deformation, cracked cells, etc.): / – Thermal scanning with a drone thermal camera to identify and zone abnormal PV arrays. / – Thermal scanning with a handheld thermal camera to assess and identify anomalies of each PV module within an array.PV module4 times/yearDrone thermal camera / Handheld thermal camera Fluke VT04panelIEC 62446-1:2017
4Count of PV modules shaded by sunlight or shadows / PV module surface free of water pooling or film build-up / PV modules free of cracks or breakage (usually caused by bird-hunting pellets or locations near roads) / Check for corrosion of PV module busbars / (usually caused by rear backsheet damage and moisture ingress)PV module4 times/yearVisual observation, statistics by time slotpanel
5Type and condition assessment of rooftop DC cable trays / Zinc coating thickness measurement / Abnormality and risk assessment of DC cable tray systemcable tray4 times/yearVisual observation, specialised equipment, statistics and assessment.system
6PV module cleaningPV module4 times/yearSpecialised toolsMwp
IIINSPECTION AND ASSESSMENT OF INVERTER OPERATING CONDITION
1Measurement and analysis of Inverter power quality: / – Check operating voltage compliance. / – Check operating frequency compliance. / – Check DC current injection. / – Check voltage harmonics. / – Check current harmonics. / – Check voltage flicker. / – Check negative-sequence component of phase voltage. / – Check power factor.Inverter1 time / yearFluke 435iisystemCircular No. 39/2015/TT-BCT and Circular No. 30/2019/TT-BCT, as amended and supplemented
2Thermal scan and detect abnormalities of Inverter: / – Check Inverter AC cable lug connection points / – Thermal scan and detect abnormalities at AC connection points. / – Thermal scan and detect abnormalities at DC MC4 connection pointsInverter4 times/yearFluke VT04, Mpc
3Check and assess the external condition and operating status of Inverter: / – Check noise level and abnormal sounds of Inverter. / – Check cooling fan of Inverter (dust, operating status, etc.). / – Check abnormal alarms and warnings of Inverter per manufacturer recommendations.Inverter4 times/yearVisual check and dedicated softwarepc
4Check and assess Inverter installation work: / – Check Inverter installation method per manufacturer recommendations. / – Check Inverter layout and installation spacing per manufacturer recommendations. / – Check sealing tightness at connection points per manufacturer recommendations.Inverter1 timepc
5Check and assess the MC4 connector type and connections at Inverter: / – Check that the MC4 connector type used at the Inverter connection meets manufacturer standards. / – Check MC4 joint tightness, water ingress risk, and abnormalities (burning, deformation, etc.) of MC4 connectors at Inverter.MC44 times/yearpc
IIIINSPECTION AND ASSESSMENT OF AC ELECTRICAL CABINET SYSTEM
1Check and assess operating status of indicator lights, voltmeter and ammeter, multimeter, electricity meter, cabinet fans, temperature controller, timer, etc.AC electrical cabinet2 times / yearcabinet
2Check and assess electrical cabinet condition: dust, air convection, corrosion, water ingress, hinges, door locks, etc.AC electrical cabinet2 times / yearcabinet
3Check and assess operating status of the AC power surge protection device.Lightning protection2 times / yearset
4Thermal scan and assess potential faults of AC electrical cabinet: / – Thermal scan and check potential faults at ACB terminal connection points. / – Thermal scan and check potential faults at MCB terminal connection points. / – Thermal scan and check potential faults at AC power cable connection points.AC electrical cabinet2 times / yearsystem
IVINSPECTION AND ASSESSMENT OF EARTHING SYSTEM
1Test and assess the earthing system of solar panels.System / earthing2 times / yearKyoritsu Kew 4105AIEEE Std 81.2-1991 / QCVN:11-TCN-18-2006
2Test and assess the Inverter earthing system.System / earthing2 times / yearKyoritsu Kew 4105AIEEE Std 81.2-1991 / QCVN:11-TCN-18-2006
3Test and assess the earthing system of electrical cabinets and transformer station.System / earthing2 times / yearKyoritsu Kew 4105AIEEE Std 81.2-1991 / QCVN:11-TCN-18-2006
4Test and assess continuity of the earthing systemSystem / earthing2 times / yearMultimeterIEEE Std 81.2-1991 / QCVN:11-TCN-18-2006
VINSPECTION AND ASSESSMENT OF MECHANICAL DETAILS
1Check coating thickness (Aluminum, Steel)Frame, mounting structure2 times / yearGTS8102system
2Survey and record corrosion and peeling of the systemFrame, mounting structure2 times / yearsystem
3Check nut tightening torqueFrame, mounting structure2 times / yearTorque wrenchsystemRandom check
VIINSPECTION AND ASSESSMENT OF MONITORING SYSTEM
1Check and assess communication line of the communication system, and any damage or instability of SmartloggerSystem / monitoring2 times / yearVisual inspectionsystem
2Check online reports of output energy and irradiance via remote monitoring system. Compare output energy with the solar meter to check for abnormal lossesSystem / monitoringDailyRemote onlinesystem
3Check alarms, events and database status – via remote monitoring systemSystem / monitoringDailyRemote onlinesystem
4Check online status report of each inverter – via remote monitoring systemSystem / monitoringDailyRemote onlinesystem

Viet Hung Power accompanies every customer from consulting and design to installation, operation and long-term maintenance.

Zalo 0945.987.333 - 097.218.5678